Stage 4
Lots 14-19
- Slabs are complete with framing work currently in progress.
Lots 20-29
- Have now commenced with all slabs now poured.
- Frame construction is due to commence over the coming weeks.
Lots 30-35
- The final row is yet to commence due to requiring that space for access.
- Once the other two rows of townhouses are at a certain stage they will then pour the final slabs.
- They aim to have the slabs down May/June.
Settlement of stage 4 will be staggered as they complete but early indication is that they will all be settled this year.